Under Construction – Krikorian – Lexington

The Krikorian Rupp project team accomplished another milestone by hoisting the rooftop mechanical equipment into position. The lift included 17 units ranging from 1,200 pounds up to 10,000 pounds. Due to the limited area to place the crane, the A.R. Mays Construction project team worked with the State of Kentucky Transportation Cabinet and City of Lexington Traffic to coordinate the lane closures and traffic detours to mitigate impact to traffic on Broadway Street.